Kitchen renovation in Mississauga
Monty's plans and builds kitchen renovations in Mississauga homes of every age, from closed-in bungalow kitchens in Applewood to builder-grade kitchens in Churchill Meadows. The layout, cabinets, counters, lighting and floor are planned together, and the same team builds them.
5.0 from 29 Google reviews Based in EtobicokePlanning a kitchen around a Mississauga house
A Mississauga kitchen renovation usually starts with the floor plan the house already has. In a 1970s or 80s two-storey, the kitchen sits at the back between a family room and a formal dining room. There's a wall on at least one side. In a 1950s bungalow it's a small room with a window over the sink. In a house built after 2000 it's already open to the family room, and the problem is the finishes and the storage.
So the first visit is about the room as it is today. Jonathan looks at which walls might come out and where the plumbing, gas and ducts run. He checks whether there's room for an island you can walk around. He also asks how you cook, how many people use the kitchen at once, and where the clutter piles up.
Cabinets and counters get chosen once the layout is settled. Counters can only be measured after the cabinets are in, so there's always a short wait between the two. That wait is in the schedule from the start, and cabinets are ordered well before demolition to keep your time without a kitchen short.
Recent kitchen projects nearby
Monty's kitchen work from other parts of the GTA.
Mississauga kitchens by type of home
The kind of house you own shapes what a new kitchen can be. These are the kitchens that come with Mississauga's main housing types, and what usually changes.
Found in Applewood, Mineola, Lakeview and Lorne Park. The kitchen is compact and closed off, often with a bearing wall between it and the dining room. Opening that wall with a beam is the biggest change you can make, and it can make a small house feel much larger.
Typical of Erin Mills, Meadowvale and Rathwood. The kitchen and eat-in nook sit beside a family room, with the dining room through a doorway. A common plan removes the wall to the family room or widens the dining room opening. The oak or melamine cabinets get replaced at the same time.
Common in Clarkson, Lorne Park and Applewood. The kitchen is on the main level with stairs going up and down beside it. Opening it to the living and dining rooms works well, but the stair wall and railings have to be part of the new layout.
Churchill Meadows, Lisgar and East Credit. These kitchens are already open, with an island or breakfast bar. Most owners keep the layout and replace the builder-grade cabinets and laminate counters, add a bigger island, and fix lighting that was never bright enough.
Galley and L-shaped kitchens in the towers around Square One. The plumbing stack and range exhaust can't move far, so the improvement comes from better cabinets, counters and lighting inside the same footprint.
What a Monty's kitchen renovation covers
Removing or opening walls, confirming whether they carry load, and adding a beam where one is needed. Islands and peninsulas are sized so people can still get past an open dishwasher.
Kitchen cabinets, pantry walls, coffee stations and built-in benches. The same millwork went into a Mississauga basement laundry we built with dark shaker cabinets and a butcher-block counter.
Quartz, natural stone, butcher block or laminate, measured once the cabinets are installed. Backsplash tile goes up after the counters are in.
Moving the sink to an island, running a gas line for a range, or adding a water line for the fridge. Appliance sizes are confirmed before cabinets are ordered so everything fits on install day.
Pot lights, under-cabinet lights, pendants over the island and new circuits for modern appliances. Older Mississauga homes sometimes need panel or wiring updates before they can carry a new kitchen.
New flooring run through the kitchen and into the rooms around it, so there's no patch left where the old cabinets stood.
Kitchen renovation cost and timeline in Mississauga
A kitchen is priced from its layout and materials, so two Mississauga kitchens of the same size can land far apart. These are the choices that move the number, and how long kitchens usually take once work starts.
What changes the price
If the sink, stove and fridge stay where they are, the plumbing, gas and electrical work stays small. Moving them, especially putting the sink in an island, adds work under the floor.
A wall that carries no load comes out fairly easily. A bearing wall needs an engineered beam, support down to the foundation and a permit. Ducts or pipes inside the wall may also need rerouting.
Stock, semi-custom and custom cabinets differ a lot in cost and lead time. Box material, door style, drawer hardware and how high the upper cabinets go all count.
Quartz and natural stone cost well above laminate, and stone prices vary a lot by slab. Waterfall ends, thick edges and islands long enough to need a second slab add to the total.
A new kitchen needs more circuits than an old one was built with. An older house may need panel work before the kitchen can be wired properly.
Flooring that stops at the kitchen costs less than flooring that runs through the whole main floor. It's worth pricing both ways.
Typical time on site
| Job | Typical time once work starts |
|---|---|
| New cabinets, counters and backsplash, same layout | 3 to 5 weeks |
| Full kitchen, same layout | 4 to 6 weeks |
| Kitchen opened to the family or dining room | 6 to 9 weeks |
| Condo kitchen | 4 to 6 weeks |
Weeks are counted from demolition day. Cabinet orders and any permit for wall removal come first and can take several weeks on their own.
Kitchen renovations across Mississauga neighbourhoods
Kitchen work changes a lot from one part of Mississauga to the next. Here's what it often looks like in different areas.
Bungalows and side-splits from the 1950s and 60s with small, separate kitchens. Opening the kitchen to the dining room is the most common plan.
Large lots and older homes, many with dated kitchens. Once a wall comes out, there's often room for a full island.
Post-war houses on deep lots. Owners often want the kitchen to open toward the backyard, with a bigger window or a patio door worked into the plan.
Two-storey homes with the kitchen, eat-in nook and family room in a row along the back. Taking down the wall between them is a frequent request.
Detached homes, semis and townhouses from the 1970s and 80s. Townhouse kitchens are narrow, so cabinet layout and storage matter more than square footage.
Open kitchens from the 2000s and 2010s with builder-grade cabinets. Replacing cabinets and counters in the same layout keeps the job shorter.
Houses from the late 1980s through the 2000s. Owners often swap the original breakfast bar for a proper island with seating.
Condo kitchens in the towers around Square One. Work follows each building's approval process and booking rules.
Questions about kitchen renovations in Mississauga
Can the wall between the kitchen and family room come down in a Mississauga two-storey?
Often, yes. The first step is finding out whether the wall carries load from the floor above. If it does, it needs an engineered beam, posts that carry the load to the foundation, and a building permit. Ducts, drains or wiring inside the wall also have to move, so we check for those at the first visit.
Our Mississauga back-split has the kitchen beside the stairs. Can it be opened up?
Usually. In back-splits and side-splits the kitchen often shares a wall with the stairs up to the bedrooms. That wall can sometimes be opened or replaced with a railing, but the stairs, the headroom and any load above have to be worked out first. We go over the options on site before anything is decided.
Our 2000s Mississauga kitchen is already open. What's worth changing?
Most owners keep the layout, which keeps both the cost and the time without a kitchen down. The usual changes are taller cabinets, quartz in place of laminate, a bigger island, a pantry wall and better lighting. If the existing floor is in good shape and the cabinet footprint stays the same, the floor can sometimes stay too.
How long will we be without a kitchen during a Mississauga renovation?
For a full kitchen, plan on four to six weeks without a working sink or stove, and longer if walls are coming out. Counters are made after the cabinets go in, and that gap is part of the time. Most families set up a fridge, microwave and kettle in the basement or dining room for those weeks.
Does a kitchen renovation in Mississauga need a permit?
Replacing cabinets, counters and appliances in the same spots usually doesn't need a building permit. Removing a bearing wall or adding new plumbing usually does, and new electrical work goes through the Electrical Safety Authority. Permit questions get sorted out early, before the schedule is set.
Can a City Centre condo kitchen in Mississauga be renovated?
Yes, within the building's rules. Most condo boards want details of the work before it starts, and some ask for a signed alteration agreement. Elevator bookings, working hours and where trades can park are built into the schedule. The plumbing stack and range exhaust usually stay where they are.
Should new flooring go in before or after the cabinets in a Mississauga kitchen?
It depends on the floor. Tile and nail-down hardwood can often go in first so the whole room is covered, which makes future layout changes easier. Floating floors usually go in after the cabinets so the cabinets don't pin them in place. If the new floor continues into the family room or hallway, it's planned as one job.
Planning a kitchen renovation in Mississauga?
Jonathan Montague looks at every job in person before a quote is written. Tell him about the room, your timing and what you want to change.